Surveying and surveying underground works of Saigon Electricity project
Surveying and surveying underground works of Saigon Electricity project is a project that Hop Nhat Bach Viet Company has just participated in construction. Hop Nhat Bach Viet specializes in cadastral surveying, topographic surveying and 3D scanning of the current status.
Surveying and surveying underground works is extremely important, especially for underground power line projects.
The location of the metro line survey and measurement in the area of District 3 – an area managed by Saigon Electric Company
Underground construction contractor: Trong Nghia Construction Mtv Co., Ltd
Surveying and measuring volume: 6km.
Purpose: to complete the positions and depths of features: electric cables, junction boxes, RMUs, electrical cabinets, transformer stations… according to the VN2000 coordinate system and the altitude of Hon Dau Hai Phong
Survey equipment:
- RTK T300 . GNSS receiver
- Hi Target V30 . RTK RTK GNSS Receiver
- Trimble R4S . GNSS receive
- Electronic Total Station Topcon ES 105
Lead time: 7 working days.
Some pictures of construction and measurement at the construction site.